PROJECT INFORMATION
Tussic Street Road Improvements (Genoa Township)
Project Description:
Reconstruction of Tussic Street Road including constructing curbs and
gutters and widening pavement to
three lanes for most of the project length. Turn lanes, traffic
signal upgrades, construction of sidewalks as well as drainage and sight distance improvements are also
included.
Project Location and Limits:
Maxtown Road to Big Walnut Road. Total project length is about 2.2
miles.
Road Closure Information:
Traffic to be maintained, with short
duration closures for installation of storm sewers, as well as a longer
duration closure with posted detour for reconstruction of Tussic just
south of Big Walnut Road.
Project Schedule:
Design engineering: December 2002 to March 2005
Right-of-way acquisition: 2004 to 2005
Utility relocation: 2005
Construction: May 2005 to December 2006 - Final completion in May 2007
Engineering Information:
Construction plans prepared by E-L Robinson Engineering of Dublin,
Ohio.
Construction Information:
Contract awarded to Shelly and Sands, Inc. of Zanesville, Ohio for $5,590,555.29.
Estimated Project Cost:
$6.3 million
|