|
Delaware County Engineer
|
CHRIS E. BAUSERMAN, PE, PS • DELAWARE COUNTY ENGINEER |
|||
|
Administration | Construction | Design | Development | Map | Operations | Permits | Stormwater Delaware County Engineer |
||||
|
PROJECT INFORMATION DEL-CR30 Sunbury Road Bridge over Big Walnut Creek (Village of Galena)
***01-14-2011: Project Alternatives*** The Delaware County Engineer's Office has developed several alternatives for this project including rehabilitation and replacement of the bridge and we would like your feedback on these alternatives. Please contact Rob Riley, Project Manager at 740-833-2400 or send your questions or comments to delcoeng@co.delaware.oh.us. No decision on the preferred alternative has been made yet!
Major Rehabilitation: Several rehabilitation alternatives were considered, including removing and replacing the bridge beams and deck (similar to what was done on the South Old 3C over Hoover Reservoir in summer 2010). None of these alternatives were feasible due to the existing foundations not being able to provide enough support for the additional width needed on the bridge. In addition, the amount of widening that could be done on the existing substructure isn't enough for the safe movement of vehicles and pedestrians. Rehabilitation has been dismissed as not being feasible.
Replacement: Two alternatives were developed for replacement of the bridge. These include a steel beam option and a prestressed concrete beam option. Both would be in a two-span configuration versus the existing 3-spans. The pier would be located on the east bank of Big Walnut Creek instead of being in the water. A preferred option for the deck layout and railing has not been selected yet.
Project Objectives:
Need: The existing bridge is structurally deficient due to normal deterioration over its 50+ year life, and is functionally obsolete based on its narrow width and inadequate railing. It does not serve the safety and mobility needs of pedestrians and bicyclists and is approaching a condition that will no longer adequately serve vehicular traffic without major repairs.
Project Location: The project site is located on the east side of downtown Galena, Ohio.
Project Background: The existing 200-foot continuous steel beam bridge was built in 1953 as part of the City of Columbus's Hoover Dam project. The bridge is in fair structural condition with notable deterioration of the steel beam superstructure and concrete deck. Rehabilitation or replacement of this bridge has been identified as a high priority project to ensure that adequate transportation is maintained in this area.
Road Closure Information:
Project Schedule: The project is currently in preliminary engineering stage. Development of alternatives is underway. Evaluation of alternatives will happen in winter 2010-11 and final design will commence in summer 2011. Construction is scheduled to begin in 2013.
Engineering Information: Questions or Comments? The Delaware County Engineer would like to hear your opinions about the project. Please contact Rob Riley, Project Manager at 740-833-2400 or send your questions or comments to delcoeng@co.delaware.oh.us.
|
||||
|
Review Delaware County's Privacy Policy Click Here |
||||
|
|
|