Delaware County Engineer

50 Channing Street

Delaware, Ohio 43015

Bidding & Contracts

Contact Us

Current Projects

Delaware County Map

Departments

Design Resource Page

Engineer's History

Links of Interest

News Archive

Permit Information

Road Closures

Search Website

Street List Database

Standards Manual

Township Engineering

Contact the Webmaster

CHRIS E. BAUSERMAN, PE, PS • DELAWARE COUNTY ENGINEER

Administration     |     Design     |     Development     |     Inspection    |    Map     |    Operations       Permits        Stormwater

Delaware County Engineer 

PROJECT INFORMATION


Smothers & Harlem Road Intersection Improvements (Delaware & Franklin Counties)
 

08-18-2011:  Public Meeting To Be Held August 29 for Smothers & Harlem Road Intersection Improvements:

The Franklin and Delaware County Engineer's Offices will be hosting an informational meeting to discuss the proposed improvement of the Harlem Road and Smothers Road intersection from 4:30 to 6:30 at the Faith Christian Center, 5325 Smothers Road (adjacent to the intersection). Please contact us with any questions or comments.

 

  Crash history exhibit (2004-07)

  Conceptual plan of modern roundabout

 
 
View Larger Map

 


Project Location:

The project site is located at the intersection of Smothers Road and Harlem Road, about 3 miles east of Westerville, Ohio.

 

Project Background:

The existing intersection has a history of accidents and congestion.  From 2004 to 2007, the accident rate was 448% of the statewide average for similar intersections.  Delays are common in the morning and afternoon peak hours, particularly on the eastbound approach to the intersection.

 

Proposed Improvements:

A single lane modern roundabout is being proposed for this intersection.  The work limits are estimated to be about 200 feet in each direction of the intersection.

 

Road Closure Information:
Traffic will be detoured during construction.  Construction is expected to last up to 3 months.

 

Project Schedule:

Detailed design of the project will be completed in late 2011.  Any additional needed right of way will be purchased in 2012.  Construction is scheduled to begin in spring of 2013.

 

Estimated Project Cost:

The current project budget is $1 million.  Both Delaware and Franklin Counties will be contributing to the project, and each county will seek additional funding through the Ohio Public Works Commission.

 