Delaware County Engineer

50 Channing Street

Delaware, Ohio 43015

Bidding & Contracts

Contact Us

Current Projects

Delaware County Map

Departments

Design Resource Page

Engineer's History

Links of Interest

News Archive

Permit Information

Road Closures

Search Website

Street List Database

Standards Manual

Township Engineering

Contact the Webmaster

CHRIS E. BAUSERMAN, PE, PS • DELAWARE COUNTY ENGINEER

Administration     |     Design     |     Development     |     Inspection    |    Map     |    Operations       Permits        Stormwater

Delaware County Engineer 

PROJECT INFORMATION


Sawmill Parkway Extension (Liberty and Delaware Townships and City of Delaware)

Visit the official Sawmill Parkway web page (www.SawmillParkway.org)

 


Sawmill Parkway Extension to Hyatts Road (DEL-CR609-4.84)

Status: Under Construction

 

Project Description:

Construction of 0.53 miles of new four-lane divided parkway from the existing terminus located one-mile north of Home Road to connect to Hyatts Road.  A modern roundabout will be built at Hyatts Road.

 

Road Closure Information:
Hyatts Road closed for up to 45 days during construction of the roundabout with a posted detour.  Traffic will be maintained throughout the remainder of the project.

 

Schedule:  

Design: 2005-06

Right of Way Acquisition:  2007-08

Construction September 2008 to August 2009

 

Engineering Information:
Construction plans prepared by Burgess & Niple, Inc. of Columbus, Ohio.

 

Construction Information:

Trucco Construction of Delaware, Ohio was awarded the contract for $2,913,266.80.

 
Estimated Project Phase Cost:
$4.25 million.

 


Future Phases - North of Hyatts Road

Status: Detailed Design and Right of Way Acquisition

 