04-27-10--Porter
Central Road Closed May 3 for 60 days
Porter Central Road will be closed
north of Centerburg Road for about 60 days starting May 3 for replacement of
a
bridge. Work on the intersection at Centerburg Road will begin in late
June or early July with a 21 day full closure of the intersection. The detour
route uses Fredricks Road.
Project Description:
Replacement of a structurally deficient steel beam bridge on Porter
Central Road just north of Centerburg Road with a precast concrete arch
culvert. Roadway approaches will also be rebuilt and the
intersection at Centerburg Road will be improved to correct deficient
sight distance and the steep grade at the intersection.
Project Location and Limits:
Porter Central Road at Centerburg Road. Reconstruction of Porter
Central Road ends about 0.10 miles north of the intersection.
Centerburg Road work includes approximately 0.13 miles of reconstruction
at the intersection.
Road Closure Information:
Porter Central Road closed for 60 days. Full intersection closure
(including Centerburg Road) for 21 days at the end of the 60 day closure
of Porter Central. Traffic to
adjacent properties maintained.
Project Schedule:
Design engineering: 2008-09
Right-of-way acquisition: 2009
Utility relocation: 2009-10
Construction: May to July 2010
Engineering Information:
Construction documents prepared by the Delaware County Engineer's
Design Department.
Construction Information:
Contract awarded to Shelly & Sands, Inc. Columbus, Ohio for $616,970
Estimated Project Cost:
$660,000
|
 |
|
|