Replacement of a narrow and structurally deficient steel pony-truss bridge. Project includes removal of existing bridge, and installing a
42-foot span precast reinforced concrete arch culvert. Approach
improvements including pavement and shoulder widening, drainage
improvements, and guardrail installation. Existing truss bridge was
donated for reuse as a park trail crossing by
Delaware County Preservation
Parks.
Project Location and Limits:
Lane Road beginning at Centerburg Road. Total project length is
about 800 feet.
Road Closure Information:
Road closed to through traffic with detour posted.
Project Schedule:
Design engineering: June 2005 to August 2007
Right-of-way acquisition: December 2007 to April 2008
Utility relocation: April to June 2008
Construction: July to October 2008
Engineering Information:
Construction documents prepared by Delaware County Engineer’s
Design
Department.
Construction Information:
Construction contract awarded
to McDaniels Construction Company of Columbus, Ohio for $381,704.48.
Precast concrete arch ordered through annual contract with Contech, Inc.
for $92,640.
Estimated Project Cost:
$519,000
 |
|
|
Old steel pony
truss built in 1916 |
|
|