|
PROJECT INFORMATION
Hoskins Road Bridge over Scioto River (Radnor
& Thompson Township
CR-183-2.84)
Project Description:
Replacement of a structurally deficient one-lane steel pony truss bridge
in very poor structural
condition. Project included removal of existing bridge and construction
of a 186 foot, three-span, post-tensioned concrete slab bridge.
This bridge is Delaware County's first post-tensioned slab bridge.
About 0.10 miles of roadway approach reconstruction on Hoskins Road was
done to improve the safety of the bridge approaches and eliminate the
sharp vertical drop at the east bridge approach. About 0.16 miles
of River Road was reconstructed to match the new, raised elevation of
the intersection with Hoskins Road. Two culverts were replaced
under River Road, and new guardrail was installed.
Project Location and Limits:
Hoskins Road from S.R. 257 to about 0.1 miles east of River Road.
Road Closure Information:
Road closed to through traffic with posted detour.
Project Schedule:
Design engineering: July 2003 to October 2004
Right-of-way acquisition: August to December 2004
Utility relocation: September to December 2004
Construction: January to October 2005
Engineering Information:
Construction documents prepared by Jones-Stuckey Ltd., Inc. of Columbus,
Ohio.
Construction Information:
Construction by Eagle Bridge Company of Sidney, Ohio. Total
construction contract amount was $1,187,351.63.
Estimated Project Cost:
$1.4 million.
|