PROJECT INFORMATION
Home Road Bridge over North
Branch of Eversole Run
(Concord Township)
Project Description:
Replacement of a narrow, twin-barrel structural plate culvert with a 28'
span concrete arch culvert. Project is being coordinated with the
construction of a turn lane for the proposed Fiddler's Creek subdivision
south of Home Road.
Project Location and Limits:
Home Road about 1/2 mile east of Concord Road. Total project length is about
50 feet. Additional turn lane construction by developer for
Fiddler's Creek subdivision.
Road Closure Information:
Road closed to through traffic with detour posted. Local traffic maintained to
nearby residences.
Project Schedule:
Design engineering: December 2006 to May 2007
Right-of-way acquisition: May to August 2007
Utility relocation: September 2007
Construction: October 2007 to April 2008
Engineering Information:
Construction plans by the Delaware County Engineer's
Design Department.
Construction Information:
Contract awarded to Vititoe Construction of Ostrander, Ohio for
$208,673. Precast concrete arch culvert supplied through
contract with Contech Bridge Solutions, Columbus, Ohio for $115,828.
Estimated Project Cost:
$360,000
 
|
Old
twin-barrel metal pipe
culvert |
New precast
concrete arch bridge |
|