Delaware County Engineer 

PROJECT INFORMATION


Liberty Road and Home Road Realignment (Liberty Township)

 

10-14-10: Liberty Road Now Open:

The newly realigned section of Liberty Road north of Home Road opened to traffic today along with red and green operation of the new traffic signal at Home Road. This work was part of a $3.1 million construction project to relocate Liberty Road North and widen both Home Road and Liberty Road south to 3-lanes with wider shoulders. All critical work is complete and over a month ahead of schedule. 

 

This project dovetails with the Home Road Grade Separation project, which includes a new bridge over the CSX Railroad. That project is scheduled for completion in summer 2011. Traffic will be maintained on Home Road until that time.

 

04-14-10--Home Road and Liberty Road Construction to Begin April 27

Widening of Home Road near Liberty Park will begin April 27. Home Road will be widened to 3 lanes including turn lanes at the park entrance and at the new intersection of Liberty Road. This work is part of a $3.1 million project to realign Liberty Road north of Home Road.

 

The initial phase of work will involve widening of Home Road while maintaining traffic.  One-lane operation will be required during some phases of work - please use caution when driving through the work zone.

 


Project Description:
Realignment of the intersection of Liberty Road (CR 9) and Home Road (CR 124) including widening of Liberty Road south of Home Road to approximately the Liberty Township Hall and widening of Home Road from the CSX railroad tracks to just east of Liberty Road.
 
Project Location and Limits:
Liberty Road from the Township Hall to a point about 1/2 mile north of Home Road.
 
Home Road from about 1/8 mile east of the CSX railroad tracks to just east of Liberty Road south.
 
Road Closure Information:
Home Road and Liberty Road traffic will be maintained, except for a 30-day closure of South Liberty Road and brief closure of North Liberty Road.
 
Project Schedule:
Design engineering: 2004 to 2007
Right-of-way acquisition: 2007 to 2009
Utility relocation: Winter 2009-10
Construction: April to December 2010
 
Engineering Information:
Construction plans prepared by American Structurepoint of Columbus, Ohio.
 
Construction Information:
Contract awarded to Double Z Construction of Columbus, Ohio for $3,135,628.
 
Estimated Project Cost:
$4.9 million including engineering, right of way and construction.

 

 