PROJECT INFORMATION
Green Meadows Drive Relocation
(DEL-750-5.53 - Orange Township)
Project Description:
Realignment of Green Meadows Drive North to intersect across from Green
Meadows Drive South at State Route 750 (Polaris Parkway). The
project is a safety improvement specifically targeted to improve safety
at the intersection with SR 750. The project is a federally funded
local project.
Project Location and Limits:
Green Meadows Drive North, beginning at SR 750 and extending
approximately 1/4 mile north. Work also being performed at the
intersection of Green Meadows Drive South and along SR 750.
Road Closure Information:
Short term road closure to perform connection to existing Green Meadows
Drive North is necessary. Traffic will be maintained on SR 750.
Project Schedule:
Design engineering: 2004 to 2006
Right-of-way acquisition: None
Utility relocation: Summer 2006 to Spring 2007
Construction: June to September 2007
Engineering Information:
Construction plans prepared by EMH&T, Inc. of Columbus,
Ohio.
Construction Information:
Contractor: Kokosing Construction Company, Inc. of Fredericktown, Ohio.
Contract amount:
$819,068
Estimated Project Cost:
$1.1 million