PROJECT INFORMATION
Green Cook Road Bridge over
Duncan Run (Harlem
Township)
04-27-10--Green
Cook Road to Close May 3 for 75 days
Green Cook Road will be closed
south of Center Village Road beginning May 3 for replacement of the
bridge over Duncan Run. The closure will last approximately 75 days.
The detour uses Center Village Road to South County Line Road to Fancher
Road, and the reverse.
Project Description:
Replacement of a structurally deficient steel beam bridge with a
prestressed concrete box beam bridge on capped pile abutments.
Minor roadway approach widening including guardrail installation and
drainage improvements.
Project Location and Limits:
Green-Cook Road about 1/4 mile south of Center Village Road.
Road Closure Information:
Green-Cook Road closed for 90 days with posted detour. Traffic to
adjacent properties maintained.
Project Schedule:
Design engineering: 2007-08
Right-of-way acquisition: 2008-09
Utility relocation: 2009-10
Construction: May to July 2010
Engineering Information:
Construction documents prepared by the Delaware County Engineer's
Design Department.
Construction Information:
Contract awarded to Crawford Construction Company of Galion, Ohio for $337,726.
Estimated Project Cost:
$370,000
|
 |
|
|
Looking north at old bridge built 1972 |
|
|