PROJECT INFORMATION
Cook Road Bridge over Eversole Run (Concord
Township)
Project Description:
Replacement of a narrow and structurally deficient two-span concrete
beam bridge of 50 foot total span length, with a 70 foot single span
prestressed concrete box beam bridge on capped pile abutments. Minor
roadway approach improvements include pavement and shoulder widening and
drainage improvements.
Project Location and Limits:
Cook Road bridge about ½ mile west of SR 745. Project limits are
approximately 200 feet east and west of the bridge.
Road Closure Information:
Cook Road closed to through traffic between Concord Road and SR 745.
Local traffic maintained to adjacent properties.
Project Schedule:
Design engineering: April 2003 to June 2004
Right-of-way acquisition: November 2004 to March 2005
Utility relocation: April 2005 to May 2005
Construction: April 2005 to September 2005
Engineering Information:
Construction documents prepared by the Delaware County Engineer’s
Design
Department.
Construction Information:
Project built by Maiden and Jenkins Company, Nelsonville, Ohio. Contract
amount: $393,700.51.
Estimated Project Cost:
$450,000
|