Delaware County Engineer

50 Channing Street

Delaware, Ohio 43015

Bidding & Contracts

Contact Us

Current Projects

Delaware County Map

Departments

Design Resource Page

Engineer's History

Links of Interest

News Archive

Permit Information

Road Closures

Street List Database

Standards Manual

Township Engineering

Contact the Webmaster

Administration     |     Design     |     Development     |     Inspection    |    Map     |    Operations       Permits        Stormwater

Delaware County Engineer 

PROJECT INFORMATION


2017 Road Improvement Program

 

2017 RIP Guide Brochure

 

Two-Week Construction Schedules:

(05-15-17)

(05-30-17)

(06-09-17)

(07-12-17)

(07-21-17)

(08-21-17)

 

Glossary of Terms:

Pavement Planing:  Grinding or milling of asphalt surfaces to remove existing asphalt surface in preparation for a new asphalt (blacktop) surface.

Stress Absorbing Membrane Interlayer (SAMI): A polymer modified liquid asphalt product applied to an existing surface to control cracking before an asphalt overlay.

Pavement Repair:  Spot removal and replacement of damaged pavement.

Paving:  Generally an asphalt (blacktop) overlay.

Chip and Seal:  A layer of stone aggregate (chips) over a coat of liquid asphalt emulsion tar (seal).  Done as an intermediate step before an asphalt overlay in order to seal cracks in existing pavement before the overlay, or as a final surface course.

Microsurfacing:  A mixture of asphalt and other mineral fillers that is applied in liquid form to existing pavement surfaces.  Seals cracks and provides a hard surface.  Requires closure of the road for approximately 2 hour.

Full Depth Reclamation:  Reconstruction of a road base by pulverization and stabilization, followed by a new asphalt and/or chip seal surface.  Requires closure of the road to through traffic for 7-10 days with local traffic maintained.

Slurry Seal:  Similar to microsurfacing but with a different combination of liquid asphalt and mineral fillers.  Generally used for low traffic streets.  Requires closure of the street for approximately 4 hours.

Project Description:
Resurfacing and preventive pavement maintenance on various county and township roads.

 

Road Closure Information:
Traffic to be maintained in the work zones using flaggers. Brief closures may also be required.


Project Schedule:
Construction: May to September 2017

 
Engineering Information:
Documents prepared by the Delaware County Engineer's Office
 
Construction Information:
Contract awarded to Shelly Company

 

Estimated Project Cost:
Total project cost = $8 million (includes all county and township work)

 

 


Review Delaware County's Privacy Policy Click Here