PROJECT INFORMATION
2008 Road Improvement
Program
Current Construction Schedule:
Click here for the
current construction schedule.
Project Description:
Resurfacing, base reconstruction,
pavement sealing, crack sealing, micro-surfacing, pavement marking,
guardrail installation and other improvements on county and township
roads.
Road Closure Information:
Traffic to be maintained in the work zones
using flaggers and a minimum of 1-lane, 2-way operation. Brief
closures may also be required.
Project Schedule:
Design engineering: Fall 2007 to spring 2008
Right-of-way acquisition: None
Utility relocation: None
Construction: May to October 2008
Engineering Information:
Construction documents prepared by the Delaware County Engineer’s
Design
Department.
Construction Information:
Contract awarded to the Shelly Company, Inc. of Columbus, Ohio
($2,976,512.20 for county and $2,421,491.80 for townships)
Estimated Project Cost:
$5.0 million (County and Township)
|