Project Schedule

Design engineering: 2006 to 2009

Right-of-way acquisition:

  • Phase 1: Spring to Fall 2008
  • Phase 2: Summer to Fall 2009

Construction:

  • Phase 1: December 2008 to August 2009;
  • Phase 2: Fall 2009 to Spring 2010

 


Engineering Information

Engineering by WD Partners of Columbus, Ohio.

 


Construction Information

Phase 1 (bridge) construction contract awarded to Eagle Bridge Company of Sidney, Ohio for $2,717,707.75

Phase 2 (roundabout) estimated cost $695,000.