Center_Village_Rd.-025-4.12-2135396-Rt_small1

Steel beam bridge built 1965

Center_Village_Rd.-025-4.16-2130726-Lt_small1

Concrete slab bridge built 1930+/-


Project Description

Replacement of two bridges on Center Village Road located about 1/2 mile west of Green Cook Road. The first bridge is a structurally deficient single span steel beam bridge over Duncan Run. The second bridge, located several hundred feet east of the first bridge is a structurally deficient and narrow concrete slab bridge. Roadway construction includes widening of pavement and shoulders near the bridges and installation of guardrail.

 

Project Location and Limits:
Center Village Road about 1/2 mile west of Green Cook Road. Project limits are approximately 200 feet east and west of the bridges.

 


Road Closure Information

Center Village Road closed to all traffic at the project site.

 


Project Schedule

Design engineering: 2007-08

Right-of-way acquisition: 2008

Utility relocation: Winter 2008-09

Construction: March 10 to July 31, 2009

 


Engineering Information

Construction documents prepared by E-L Robinson Engineering of Ohio.

 


Construction Information

R&I Construction of Tiffin, Ohio. Contract amount $478,037.

 


Estimated Project Cost

$699,000